[ PC ] Field guide // Owners & site supervisors

Practical Completion in Queensland: The Defects Document and a Room-by-Room Handover Checklist

Practical completion starts the defect clocks and usually triggers the final payment. Walk the house room by room, leave with a signed defects document, and diary the deadlines that follow.

Published
Read
7 min
Region
SEQ + Hervey Bay
File
PC-8288
Animated schematic: a floor plan of a finished house at practical completion. A LiDAR scanner in the hallway sweeps the plan, and each glowing defect node it passes, such as grout in the bathroom or a chipped benchtop, changes from flagged to logged. 15 040 9 760 GARAGE 4.0 × 4.8 BED 2 4.0 × 5.0 LDRY BATH BED 3 3.0 × 3.4 MASTER 3.9 × 4.8 LIVING · KITCHEN 7.1 × 5.0 STUDY ALFRESCO ENS STN-01 D-01 GROUTFLAGLOGGED D-02 D-03 D-04 BENCH CHIPFLAGLOGGED D-05 PAINTFLAGLOGGED D-06 D-07 D-08 N 04 m1:100 FLAGGEDLOGGED

Handover sequenceFixing → 12-month window

  1. Fixing stage
  2. Final inspection
  3. PC walkthroughRecord
  4. Keys
  5. Defects fixed
  6. 12-month window

Record the whole house at the walkthrough, before furniture goes in and before the first repair

In this guide9 sections · 7 min read
  1. 01What is practical completion?
  2. 02Before the walkthrough: what to bring
  3. 03The new build handover checklist, room by room
  4. 04The defects document: agreed, disputed and fix-by dates
  5. 05Certificates and documents to collect
  6. 06The 12-month window and other deadlines
  7. 07If the builder refuses to fix defects
  8. 08Record the house at handover
  9. 09Practical completion: FAQs
// Module index · 09 modules
  1. MOD 01What is practical completion?
  2. MOD 02Before the walkthrough: what to bring
  3. MOD 03The new build handover checklist, room by room
  4. MOD 04The defects document: agreed, disputed and fix-by dates
  5. MOD 05Certificates and documents to collect
  6. MOD 06The 12-month window and other deadlines
  7. MOD 07If the builder refuses to fix defects
  8. MOD 08Record the house at handover
  9. MOD 09Practical completion: FAQs

Practical completion is the day the house stops being the builder's site and starts being your home. It's also the day the final payment usually falls due, the defects list is agreed, and the clocks on your defect rights start running. What you raise at the handover walkthrough, and what's on record about the house that day, shapes every conversation about defects that follows.

This guide explains what practical completion means under a Queensland building contract, how to run the handover inspection room by room, what goes on the defects document, the deadlines to diary, and what to do if a builder refuses to fix defects. It's written for owners two to four weeks out from handover, and for site supervisors preparing for it. It's general information, not legal advice.

What is practical completion?

A home reaches practical completion when the building work is finished in line with the contract, the plans and specifications and the building rules, apart from minor defects or minor omissions. It has to be suitable to live in: weatherproof, with power and water connected, working as a normal home. Touch-up painting can still be outstanding; a leaking shower or a missing kitchen can't.

Your contract says how the builder tells you practical completion has been reached, usually with written notice of the date and an invitation to the handover inspection. The final progress claim normally follows, so check the contract for how long you have to pay and what has to be handed over first.

Before the walkthrough: what to bring

Ask for the walkthrough date in writing as soon as the builder can give it, and book anyone you want there, such as an independent building inspector. Then gather what you'll check the house against:

  • The contract, plans and specification. The finished house is checked against these, not against the display home.
  • Your selections schedule and every signed variation. Colours, tiles, tapware, appliances and anything changed during the build.
  • A torch, a bucket of water and a phone. The torch at a low angle shows paint and plaster flaws, the bucket tests floor falls, and the phone photographs each defect where it is.
  • Time. Allow a few hours for a typical new home. Rushed walkthroughs are where defects get missed.

The new build handover checklist, room by room

Work through the house one area at a time: wet areas, joinery, paint and linings, doors and windows, the roof and external work, services and appliances, then the documents and anything not yet supplied. For each defect, note exactly where it is, whether the builder agrees it's a defect, and the date it will be fixed.

The practical completion inspection checklist below does that for you. Tick Agreed or Disputed against each item, add the location and a fix-by date, then copy the draft defects document into an email to your builder or print it for the walkthrough.

Handover ledger // PC walkthrough

Walk it room by room. Leave with a defects document.

Tick Agreed when the builder accepts a defect and set the date it will be fixed. Tick Disputed when they don't. Add where each one is, then copy the draft defects document into an email to your builder.

Document header
WAWet areas
Item Agreed Disputed Fix-by date
WA-01 Tiles: no cracked, chipped or drummy tiles, and even joins between tiles
WA-02 Grout and silicone: no gaps, cracks or discolouration, and silicone at every change of plane
WA-03 Floor falls: water runs to the floor waste with no ponding (test with a bucket)
WA-04 Shower screen: seals fitted, door swings and closes, no leaks with the shower running
WA-05 Tapware: hot and cold the right way round, no drips, mixers and outlets secure
WA-06 Toilet: secure to the floor, flushes and refills, no weeping at the pan
WA-07 Exhaust fan runs; vanity, mirror and accessories fixed firm
WA-X
JNJoinery
Item Agreed Disputed Fix-by date
JN-01 Doors and drawers align, open fully and close without catching
JN-02 Benchtops: no chips or scratches, joins tight, sealed at the sink and cooktop
JN-03 Kickboards, end panels and fillers fitted, with no gaps to walls
JN-04 Handles and hardware match the selections and are secure
JN-05 Robe, linen and pantry shelving and rails as shown on the plans
JN-06 Splashback sealed at the benchtop and around power points
JN-X
PTPaint & linings
Item Agreed Disputed Fix-by date
PT-01 Walls and ceilings checked with a torch at a low angle: patchiness, roller and sanding marks
PT-02 Plasterboard: no visible joins, nail pops or cracks at the cornice
PT-03 Cut-in lines clean at ceilings, skirtings and architraves
PT-04 Colours and sheen match the selections schedule
PT-05 No scuffs, chips or damage on walls, doors, frames and skirtings
PT-X
DWDoors & windows
Item Agreed Disputed Fix-by date
DW-01 Every internal door opens, closes and latches without binding
DW-02 Locks: every lock works, keys supplied and labelled
DW-03 Windows and sliding doors open, close and lock smoothly
DW-04 Flyscreens and security screens fitted and undamaged
DW-05 Glass free of scratches and chips (check in daylight)
DW-06 Door stops, seals and weather strips fitted
DW-X
RXRoof & external
Item Agreed Disputed Fix-by date
RX-01 Gutters and downpipes connected, no leaks, stormwater running away from the house
RX-02 Roof covering, flashings and eaves: no visible damage (check from the ground)
RX-03 Brickwork or cladding: no cracks, mortar smears or damage; weep holes clear
RX-04 Driveway, paths and paving: no cracks; surfaces fall away from the house
RX-05 External taps, lights and power points work
RX-06 Site cleaned up, with rubbish and leftover materials removed
RX-X
SVServices & appliances
Item Agreed Disputed Fix-by date
SV-01 Every power point, switch and light works
SV-02 Smoke alarms in place as shown on the plans, and they sound together when tested
SV-03 Hot water reaches temperature at every outlet
SV-04 Air-conditioning units heat and cool, and condensate drains
SV-05 Appliances installed and working: oven, cooktop, rangehood, dishwasher
SV-06 Data, TV and NBN points as shown on the plans
SV-X
DCDocuments & omissions
Item Agreed Disputed Fix-by date
DC-01 Final inspection certificate (Form 21) from the building certifier
DC-02 Certificates for waterproofing, electrical, plumbing and gas work
DC-03 Appliance warranties, product manuals and the builder's maintenance information
DC-04 Keys, remotes, alarm codes and meter details handed over
DC-05 Items in the contract not yet installed or supplied (minor omissions)
DC-X

// Preview the document

The record behind the listA list says what was wrong on the day. A dated 3D record of the whole house shows what wasn't, which is what later arguments turn on.

Your ticks, notes and dates stay in this browser only, so you can refresh without losing them. General information only, not legal advice. The builder's signed defects document is the one that counts.

The defects document: agreed, disputed and fix-by dates

If you raise minor defects or omissions at handover, they're recorded in a defects document completed during the walkthrough. It lists:

  • the defects and omissions you and the builder both agree exist, and when the builder will fix them;
  • separately, the defects you believe exist that the builder doesn't agree with.

Both of you sign it, and you keep a signed copy. Raise everything you can see on the day. Anything left off is easier for the builder to say appeared after handover.

Certificates and documents to collect

Before you make the final payment, ask for the paperwork that goes with the house:

  • the final inspection certificate (Form 21) from the building certifier;
  • certificates of inspection and compliance for waterproofing, electrical, plumbing and gas work;
  • appliance warranties, product manuals and the builder's maintenance information;
  • keys, remotes, alarm codes and meter details.

Appliance faults after handover generally go to the supplier under its warranty, not to the builder.

The 12-month window and other deadlines

Practical completion starts several clocks at once, and they don't run for the same length of time:

  • Telling the builder. The builder has to fix defects noticed at handover or within 12 months of completion, and you need to tell them about a defect within 12 months of noticing it.
  • QBCC complaints. For non-structural defects, a defective work complaint generally has to be made within 12 months of practical completion. Structural defects have longer limits, counted from when you notice them.
  • Home warranty. Non-structural cover needs the defect to appear within 6 months of completion, with the claim made within 7 months. Structural cover runs for 6 years and 6 months, with claims within 3 months of noticing.

Diary the dates on the day you get the keys, and check the QBCC's current rules for your contract.

If the builder refuses to fix defects

Start in writing. List each defect, where it is and the date on the defects document, and give the builder a reasonable time to respond. If that doesn't resolve it, you can lodge a defective work complaint with the QBCC within its time limits. The QBCC may inspect, and where it finds defective work it can direct the builder to fix it. If a direction isn't followed, or the builder can't be found or has gone out of business, the home warranty may apply.

While it runs, keep everything together: the defects document, photos, emails and any record of the house at handover are what everyone will be looking at.

Record the house at handover

Most arguments after handover come down to one question: was it like that when the keys changed hands? A defects list says what was wrong on the day. It doesn't show everything that wasn't, and that's usually what later disputes turn on.

A post-construction audit captures the whole house in 3D at the walkthrough: dated, to scale and walkable, room by room, before furniture goes in and before the first repair. Builders book it as Stage B of the Builder Assurance Bundle, paired with a frame record taken before the plasterboard goes on. Owners can book it on its own. It sits alongside the certifier's inspection and the defects document; it doesn't replace either, and it doesn't decide who's responsible for a defect.

The tour is hosted for six months, then archived and reinstated on request. Our as-built guide explains how the frame and handover records work together through the defects period.

Practical completion: FAQs

Q.01

What is practical completion in Queensland?

It's the stage when the work is finished in line with the contract, plans, specifications and building rules, apart from minor defects or omissions, and the house is suitable to live in. It's usually when the final payment falls due.

Q.02

Can I refuse to accept handover?

If the work isn't at practical completion as your contract defines it, raise that with the builder in writing before the final payment. Minor defects alone usually don't stop practical completion; they go on the defects document. Get advice before withholding a payment.

Q.03

What should a new build handover checklist include?

Every room: wet areas, joinery, paint and linings, doors and windows, roof and external work, services and appliances, plus the certificates, warranties, keys and anything in the contract not yet supplied.

Q.04

How long does a builder have to fix defects?

Agreed defects on the defects document should be fixed by the dates it sets, or as soon as practical. Your contract may set a timeframe too. The builder also has to fix defects you notice within 12 months of completion.

Q.05

What if my builder refuses to fix defects?

Put the request in writing with the details and a timeframe. If that fails, lodge a defective work complaint with the QBCC within its time limits. It can direct the builder to fix defective work.

Q.06

Should I get an independent inspection before handover?

Many owners do. An independent building inspector can attend the walkthrough with you and help list defects before you sign the defects document.