Disputing a Builder's Progress Claim or Variation in Queensland

A progress claim or variation that doesn't match the site? Before you hold back payment, check the contract, the variation paperwork and what was built on the claim date.

Published
Updated
Read
6 min
Region
QLD
File
PC-3536
Claim reconciliation · PC-07Resident owner route
PROGRESS CLAIM · STAGE LEDGERBASEFRAMEENCLOSEDFIXINGPCCLAIMEDON SITEVARIATION · QBCC ACT SCH 1BBUSINESS DAYS →DISPUTE ROUTE · RESIDENT OWNERNOTICEIN WRITINGQBCCEARLY RESOLUTIONQCATDECIDES · ORDERSBIF ACT ADJUDICATION · N/A, RESIDENT OWNERREC · CLAIM DATEIN DISPUTEAGREED IN WRITINGCOPY ≤ 5 BUSINESS DAYSWORK STARTSAGREED BEFORE WORK
Illustrative · not to scale · general information, not legal advice
In this guide6 sections · 6 min read
  1. 01What a progress claim can include
  2. 02When a variation is valid
  3. 03Which dispute route applies to you
  4. 04Check the claim before you pay it
  5. 05What was built on the claim date
  6. 06Disputing a builder's claim: FAQs
// Module index · 06 modules
  1. MOD 01What a progress claim can include
  2. MOD 02When a variation is valid
  3. MOD 03Which dispute route applies to you
  4. MOD 04Check the claim before you pay it
  5. MOD 05What was built on the claim date
  6. MOD 06Disputing a builder's claim: FAQs

When a progress claim or a variation invoice doesn't match what you can see on site, the first instinct is to stop paying. In Queensland, that can put you in breach of your own contract if the claim turns out to be valid. Disputing a builder's invoice starts with three checks: does the claim match the contract, was the variation agreed properly, and what shows the work on the claim date?

This guide covers the rules for progress claims and variations in Queensland, which dispute route applies to you, and how to raise a dispute in writing. It's written for owners building a home to live in, with notes for builders whose claims are being disputed. It's general information, not legal advice.

What a progress claim can include

A progress claim is a request for payment at a stage, or an interval, set out in your contract. Under the QBCC Act, a builder can't claim an amount, other than the deposit, unless it relates directly to the progress of the work on site and is no more than the value of that work.

  • The contract defines the stages. The legislation no longer sets payment stages, so each claim is measured against the contract's own definition of the stage, usually base, frame, enclosed, fixing and practical completion.
  • A claim can't run ahead of the work. The QBCC's example: a builder can't claim more than 50% of the contract price, including the deposit, until at least 50% of the work on site is done.
  • A valid claim is due on time. If the stage is complete as the contract defines it, the claim is generally payable by the due date in the contract.

Our guide to construction loan stages explains what each stage usually includes, and what a lender checks before it releases a drawdown.

When a variation is valid

A variation is a change to the work or the contract price after the contract is signed. The QBCC Act sets out how it has to be done:

  • In writing, before the work starts. The builder must give you the variation in writing, and you must agree to it in writing, before the variation work starts. The only exception is urgent work where a written copy first isn't reasonably practicable.
  • What it must say. The document has to describe the variation, state the date of the request and the change to the contract price (or how it will be worked out), and give the builder's reasonable estimate of any delay it will cause.
  • Your copy. You must get a written copy before the variation work starts, or within 5 business days of agreeing to it, whichever comes first.
  • When it can be charged. A builder can't require payment for a variation before the variation work starts.

If a variation turns up on an invoice with no written agreement behind it, raise it in writing before you pay. Whether the builder can still be paid for the work depends on the contract and the circumstances, so get advice before you refuse. Many site-cost variations start as provisional sums in the tender, which Before the Slab explains.

Which dispute route applies to you

Queensland's fast payment-claim adjudication under the Building Industry Fairness (Security of Payment) Act, the BIF Act, generally doesn't apply to a contract for domestic building work where a resident owner is a party. If you're building a home to live in, the route runs through the contract's dispute clause instead:

  1. Raise it in writing. Talk to the builder first, then give written notice of the disputed items by email or post, with a timeframe to reply. The QBCC uses 14 days as an example.
  2. QBCC early dispute resolution. While the contract is still active, the QBCC can work with both sides to reach an agreement. It can't order anyone to pay.
  3. QCAT. The Queensland Civil and Administrative Tribunal can decide the dispute and order payment. It needs a letter from the QBCC showing you've been through its process first.

Investors building to rent or sell, and subcontractors, are usually covered by the BIF Act instead. Under it, a payment schedule answering the claim is due within 15 business days, or sooner if the contract says so, and missing it can make the full claimed amount payable.

If the builder has stopped work altogether, the rules change: our guide to terminating a building contract covers the notices, the home warranty deadlines and recording the site before it changes hands.

Check the claim before you pay it

Most disputes turn on three questions: does the claim match the contract's stage definition, was the variation agreed in writing first, and what evidence is there of the work on the claim date? Work through them below. You'll get the likely next step and a draft notice outline you can copy and fill in.

Claim check // general information, not legal advice

Check the claim before you pay it.

Answer a few questions about the claim or variation in front of you. You'll get the likely next step and a draft notice outline to copy and fill in. Nothing you pick is stored or sent.

Who's checking the claim?
What are you checking?
Does the claim match the contract's stage definition?
Was the variation agreed in writing before the work started?
Did the owner get a written copy within 5 business days of agreeing?
What shows the work on the claim date?

Awaiting answers

0 / 4 answered

Answer the questions to see the likely next step, the dispute route and a draft notice outline.

General information, not legal advice. Contracts differ, so check yours and get advice before you hold back a payment. QBCC: Contract or payment dispute (opens in a new tab)

What was built on the claim date

Most progress-claim disputes come down to one question: what stage had the work reached on the day it was claimed? By the time it's argued about, the next trade has been through and the frame is behind plasterboard. Photos rarely settle it, because they're partial, hard to place in the house, and easy to argue about.

A dated 3D record of the stage being claimed shows the whole site as it was on that day, room by room. For owners, it's evidence to attach to a written notice. For builders, it's proof that the claimed stage was reached. That's what the pre-plaster audit records at frame stage, and the Builder Assurance Bundle adds a second record at handover. Our as-built guide covers how a frame-stage record is captured and used. It doesn't replace the certifier's inspections.

Dated stage record // owners & builders

Proof of the stage, dated on the day it's claimed

A dated 3D record of the stage being claimed shows the whole site, room by room, as it was on that day. Owners can attach it to a written notice. Builders use the same record to back the claim, and the Builder Assurance Bundle adds a second record at handover.

Disputing a builder's claim: FAQs

Q.01

Can I refuse to pay a progress claim?

You can dispute a claim that doesn't match the contract, but how you do it matters. Check the contract's process for disputing a claim, give written notice of what you dispute and why, and get advice before you hold back a payment. Withholding a valid payment can put you in breach of the contract.

Q.02

Does a variation have to be in writing?

Yes. In Queensland a variation has to be agreed in writing before the variation work starts, except for urgent work where a written copy first isn't reasonably practicable. You should get a written copy before the work starts, or within 5 business days of agreeing, whichever comes first.

Q.03

How do I dispute a builder's invoice in Queensland?

Talk to the builder, then give written notice of the disputed items with a timeframe to reply. If that doesn't resolve it, apply to the QBCC's early dispute resolution service while the contract is active. If it's still unresolved, QCAT can decide the dispute once you have the QBCC's letter.

Q.04

Can I use BIF Act adjudication as a homeowner?

Generally not, if you're a resident owner building a home to live in. Adjudication under the BIF Act is mainly used between head contractors and subcontractors, and where the owner isn't a resident owner, such as an investor.

Q.05

What if the builder is delayed?

Check the contract's clause on extensions of time. A variation document has to state the builder's reasonable estimate of any delay it causes, and most contracts set out how other delays are claimed and what happens if the completion date is missed. Raise delays in writing as they happen.

Q.06

Does a 3D record settle a dispute?

No record guarantees an outcome. A dated 3D record shows what the site looked like on the day it was captured, which gives both sides the same reference. It doesn't replace the certifier's inspections, the contract or legal advice.